MIS Test Integration
EN RU
Projects
Our Portfolio

Projects

Project 1 - Slide 1 Project 1 - Slide 2 Project 1 - Slide 3 Project 1 - Slide 4
Services Turnaround Maintenance

Shut Down Project

Location Kazakhstan
Year 2024

Client: NCOC Bolashak Plant

As part of the SD 2024 Project, a team of 96 specialists from Sashma-MIS successfully completed key turnaround activities.

The work was carried out with high efficiency, full compliance with standards, and on-time completion of all stages.

Project 2 - Slide 1
PFP Protective Coatings Fabrication Installation

Wellhead Control Platform

Location Kazakhstan
Year 2023

Client: NCOC

WCP Fabrication and Offshore Installation for NCOC – Kashagan Field Executed by KCOI and MSS.

Исполнители: KCOI и MSS.

PFP Protective Coatings: Intershield 300, Chartek 7, Interthane 990.

Project 3
PFP Protective Coatings Fire Protection

KARACHAGANAK PROCESSING COMPLEX (KPC)

Location Kazakhstan
Year 2017

Client: KPO

Maintenance scope where client decided to switch from Cementitious to Intumescent Epoxy Fire Protection.

PFP Protective Coatings: Intergard 251, Chartek1709.

Project 4 - Slide 1
Water Treatment

Reverse Osmosis

Location Kazakhstan
Year 2023

Client: KPO

Envirotech has successfully supplied and commissioned a containerized High Brackish Reverse Osmosis Desalination Plant.

Capacity of 500 m3/day to compensate the shortage of fresh water.

Project 5
PFP Protective Coatings

Future Growth Project

Location Kazakhstan
Year 2016-2019

Client: TCO (Chevron)

Successful Completion of the $45 Billion Future Growth Project (FGP-WPMP) for Tengizchevroil (TCO).

Project 6
PFP Protective Coatings

KSU Project

Location Kazakhstan
Year 2025

Client: PSI Group

Supplying of International Paint for Electrical Substations for TCO

PFP Protective Coatings: Interzinc52, Intergard 475HS, Interthane990.

Project 7 - Slide 1 Project 7 - Slide 2 Project 7 - Slide 3 Project 7 - Slide 4 Project 7 - Slide 5
Water Treatment

PAC Coagulant Chemical Dosing Skid

Location Kazakhstan
Year 2023

Client:NCOC

As part of the project, the PAC Coagulant Chemical Dosing Skid was developed and implemented for precise injection of coagulant chemicals into wastewater. The system is configured to deliver up to 17.1 L/h at 4 bar pressure, ensuring efficient removal of suspended solids and improved water quality. The solution was integrated at the client’s facility and tailored to meet the needs of large industrial operations, including the oil and gas, mining, food and beverage, agriculture, and construction sectors.

Project 8
PFP Protective Coatings

Steel Structures for Fujairah

Location UAE
Year 2024

Client:Kelly Steel Engineering

Steel Structures for Fujairah open stadium

Project 9 - 1 Project 9 - 2
PFP Protective Coatings

Coat System and specialized internal coating

Location UAE
Year 2024

Client:Magnum Technologies

Our 3 Coat System and specialized internal coating

Was used for:- Airproduct E house - Emerson E House - Haliburton tanks

Project 10
PFP Protective Coatings

Topcoat for Repainting of Mining Heavy Machineries

Location UAE
Year 2024

Client:Soutwest Middle East

Our Topcoat was used for Repainting of Mining Heavy Machineries

Project 11 - 1 Project 11 - 2
PFP Protective Coatings

Coat for Halliburton stock tanks and trailers

Location UAE
Year 2024

Client:Al Shirawi

3 Coat system was used for Halliburton stock tanks and trailers.

Project 12
PFP Protective Coatings

LPG plant PFP application

Location Kazakhstan
Year 2025

Asset Owner:NCOC

PFP Protective Coatings:KCOI

Product:30 tons of Chartek 2218

Project 13
PFP Protective Coatings

Onshore PFP application

Location Kazakhstan
Year 2025

Client:NCOC

Applicator:PSI

Product:25 tons of Chartek 2218

Project 14
PFP Protective Coatings

Onshore PFP application

Location Kazakhstan
Year 2025

Client:KPO

Applicator:PCE

Product:35 tons of Chartek 2218

Project 15
FBE

KPO pipeline

Location Kazakhstan
Year 2026

Main contracto:KSP steel

Sub contractor:Qarmet

Product:Nap-Gard

Project 14 - 1 Project 14 - 2 Project 14 - 2
PLC

PLC Panel – Suzuki Electronics

Location India
Year 2025

Client: Suzuki Electronics

Applicator:MIS Tech Solutions

Product:PLC Control Panel

Project 15 - 1 Project 15 - 2
VFD

CONTROL TECHNIQUES C200 VFD PANEL 75KW

Location Kazakhstan
Year 2025

Client:Shashma MIS LLP

Applicator:MIS INTERNATIONAL PVT LTD

Product: 75 KW C200 VFD Control Panel APPLICATION-- PUMP

Project 16 - 1 Project 16 - 2
VFD

CONTROL TECHNIQUES C200 VFD PANEL 90KW

Location Kazakhstan
Year 2025

Client:Shashma MIS LLP

Applicator:MIS INTERNATIONAL PVT LTD

Product: 90 KW C200 VFD Control Panel

Application:Pump

Project 17 - 1 Project 17 - 2
VFD

CONTROL TECHNIQUE NE300 11KW X 3 VFD PANEL – Karnataka PAPER MILL

Location India
Year 2024

Client:Karnataka PAPER MILL

Applicator:MIS INTERNATIONAL PVT LTD

Product:11KW NE 300 VFD Control Panel

Application:Conveyor

Project 18 - 1 Project 18 - 2
VFD

CONTROL TECHNIQUE - NIDEC VFD PANEL – 18KW X 2 – PRABHULINGESHWAR SUGAR PVT LTD.

Location India
Year 2026

Client:PRABHULINGESHAWAR SUGAR PVT LTD

Applicator:MIS INTERNATIONAL PVT LTD

Product: 18KW NE 300 VFD Control Panel

Application:CANE HANDLING

Project 19 - 1 Project 19 - 2
PLC

CONTROL TECHNIQUE NIDEC VFD PANEL 18KW X3, - J D CHEMICAL INDUSTRIES PVT LTD.

Location India
Year 2024

Client:J D CHEMICAL INDUSTRIES PVT LTD

Applicator:MIS INTERNATIONAL PVT LTD

Product: 18KW NE 300 VFD Control Panel

Application:CENTRIFUGAL

Project 20
PLC

CONTROL TECHNIQUE NIDEC VFD PANEL 355KW X1 VFD ICPL SUGAR FOR PUMP APPLICATION

Location India
Year 2024

Client: ICPL SUGAR LTD

Applicator:MIS INTERNATIONAL PVT LTD

Product: 18KW NE 300 VFD Control Panel

Application:PUMP

Project 21 - 1 Project 21 - 2
PLC

CONTROL MCC AND VF PANEL SUPPLIED TO POWER PLANT ENGINEERING

Location India
Year 2025

Client:POWER PLANT ENGINEERING

Applicator:MIS INTERNATIONAL PVT LTD

Product:22KW , 4KW, 7.5KW VFD Control Panel

Application:ROLLER MACHINE AND TUBE BENDING

Project 22 - 1
SUPPLY PROTECTIVE COATING

SUEZ METAL FACTORY

Location Egypt
Year 2021

Client:Suez Metal

Epoxy coating supply for the Suez Metal factory – 400,000 m².

Executed by:MIS

Protective Coatings: Interseal 1052, Interthane 990.

Project 23
SUPPLY PROTECTIVE COATING

INFRASTRUCTURE PROJECTS

Location Egypt
Year 2021-2026

Client:Various clients

Protective coating systems supplied for various infrastructure steel structures.

Executed by:MIS

Protective Coatings: Interzinc 52, Intergard 475HS, Interthane 990.

Project 24 - 1
SUPPLY PROTECTIVE COATING INFRASTRUCTURE

ICONIC TOWER – NEW CAPITAL

Location Egypt
Year 2021-2022

Client:CSCEC

Passive fire protection for landmark towers: Iconic Tower (New Capital CBD), Almina Tower, Key of Life and more.

Executed by:MIS

PFP Coatings:Interchar 1260, Interchar 1290, Interchar 212.

Project 25 - 1 Project 25 - 2 Project 25 - 3 Project 25 - 4 Project 25 - 5 Project 25 - 6
SUPPLY PROTECTIVE COATING TANK LINING M&R

TANKS LINING & EXTERNAL PAINT

Location Egypt
Year 2021-2023

Client:Amreya, EPC, Alexandria Petroleum,ELNG, Zohr, EMC, MIDOR, Burullus Gas Refinery, Petrojet, BP, Total, SUMED, etc

M&R blasting and painting of internal and external storage tanks – Oil & Gas, Egypt.

Executed by:MIS

External: Interzinc 52, Intergard 475HS MIO, Interthane 990

Internal Lining: Interline 850, 984, 925, 339, 9670.

Project 26
SUPPLY PROTECTIVE COATING PIPELINES NEW CONSTRUCTION

DABAA PROJECT

Location Egypt
Year 2024-2025

Client:DOSAAN

New construction coating of seawater intake pipelines and equipment.

Executed by:MIS

Protective Coatings: Interzone 954, Interzinc 52, Interseal 670HS, Interthane 990

Project 27 - 1
SUPPLY PROTECTIVE COATING PIPELINES M&R

CRUDE OIL PIPELINE

Location Egypt
Year 2021-2022

Client:SUMED, Misr Petroleum

M&R coating of crude oil pipelines

Executed by:MIS

Protective Coatings: Interseal 670HS, Interthane 990.

Project 28 - 1
SUPPLY PROTECTIVE COATING PIPELINES LINING

POTABLE & TREATED WATER PIPELINES

Location Egypt
Year 2022-2023

Client:Various clients

Potable and treated water pipelines – Haya Karima initiative.

Executed by:MIS

Protective Coatings: Interline 925P, Interzone 954, Interseal 670HS.

Project 29
SUPPLY PROTECTIVE COATING INSPECTION

METRO LINE 4 & METRO GARAGE

Location Egypt
Year 2022

Client:NAT Egypt

Supply of coatings and PFP, with engineering and inspection services.

Executed by:MIS

PFP Coatings: Interchar 1190, 1290, 1260, 212.

Project 30 - 1
SUPPLY PROTECTIVE COATING INSPECTION

ADLY MANSOUR HUB

Location Egypt
Year 2022

Client:NAT Egypt

Supply of coatings and PFP, with engineering and inspection services.

Executed by:MIS

PFP Coatings: Interchar 1190, 1290, 1260, 212.

Project 31 - 1
SUPPLY PROTECTIVE COATING

SAMSUNG FACTORY

Location Egypt
Year 2023

Client:Samsung

Coating and passive fire protection supply for the Samsung factory.

Executed by:MIS

Cellulosic PFP System: Interseal 1052, Interchar 1260, Interthane 990.

Projects
Project 32
HYDROCARBON PFP TRAINING

MIS PFP TRAINING SCHOOL

Location Egypt
Year 2022-2026

Client:MIS

Hands-on Chartek hydrocarbon passive fire protection training in Egypt.

Executed by:MIS

PFP Coatings: Chartek

Project 33 - 1
SUPPLY HYDROCARBON PFP NEW CONSTRUCTION

DUSCO PROJECT

Location Egypt
Year 2025-2026

Client:DUSCO

Supply of hydrocarbon PFP for new construction – 2,000 m²

Executed by:MIS

PFP Coatings: Chartek 2218

Project 34 - 1
SUPPLY HYDROCARBON PFP NEW CONSTRUCTION

ZOHR PROJECT

Location Egypt
Year 2024-2025

Client:Zohr

Supply of hydrocarbon PFP for new construction – 700 m²

Executed by:MIS

PFP Coatings: Chartek 2218, Chartek 1709.

Project 35
SUPPLY HYDROCARBON PFP M&R

BURULLUS REFINERY

Location Egypt
Year 2024-2026

Client:Burullus Refinery

Supply of hydrocarbon PFP for M&R – 11,000 m².

Executed by:MIS

PFP Coatings: Chartek 2218

Project 36 - 1
HYDROCARBON PFP M&R

ANRPC REFINERY

Location Egypt
Year 2024

Client:ANRPC

M&R hydrocarbon PFP – 1,000 m².

Executed by:MIS

PFP Coatings: Chartek 2218

Project 36 - 1
SUPPLY HYDROCARBON PFP M&R

ABU QIR PETROLEUM

Location Egypt
Year 2023-2026

Client:Abu Qir Petroleum

Continuous supply of hydrocarbon PFP for M&R – 3,500 m².

Executed by:MIS

PFP Coatings: Chartek 2218

About Us
Футтер